Dumfries and Galloway Council has moved the start of planned sewer diversion works on the Whitesands until after Christmas and new year.
The works were due to begin on 30 November 2026 as part of the Whitesands Project. They will now start at 9am on Tuesday 5 January 2027.
The decision follows further consideration of the effect the works could have on the town centre during the busy Christmas trading period, including concerns raised by businesses, residents and community groups.
Moving the start date means the Whitesands will remain fully open throughout December and over Christmas and new year, with the planned traffic restrictions now beginning in January.
The sewer diversion works are an essential part of the wider Whitesands Project and need to be completed before later stages of the project can progress.
Councillor Andy Ferguson, Chair of the Economy and Infrastructure Committee, said:
“We have listened carefully to the concerns raised about starting these works in the run-up to Christmas.
“Christmas is an important trading period for Dumfries town centre, and after looking again at the programme we believe moving the start of the works to January is the right thing to do.
“This means people can continue to access the Whitesands as normal throughout the festive period, and we would encourage everyone to support our town centre businesses over Christmas and new year.
“These works are still an important part of the Whitesands Project and will begin in January. We will continue to work with businesses and others affected to keep disruption to a minimum and make sure people know what to expect.”
Councillor Tony Berretti, Vice-Chair of the Economy and Infrastructure Committee, said:
“The Whitesands Project is a major investment in the future of Dumfries, providing greater protection from flooding as well as improving the riverside and public spaces.
“Moving these works to January allows us to protect the important Christmas trading period while keeping the wider project on track.
“We know there will be disruption as work progresses, and we will continue to work with businesses and people affected to maintain access wherever possible and keep everyone informed.”
The £68.6 million Whitesands Project will provide a 1-in-75-year standard of flood protection, helping to reduce flood risk to homes, businesses and key infrastructure. It will also deliver improvements to walkways, landscaping and public spaces along the River Nith.
The council is contributing £13.7 million towards the project, with £54.9 million of funding from the Scottish Government.
The project is being delivered in phases across the Whitesands area. Further information about the January works, including traffic management arrangements, diversion routes and access, will be provided before work begins.